Community Corner

250 Down, 100 More to Go

Georgia DOT says concrete panel installation is progressing well.

Work continues this week on concrete panel installation in downtown Winder. So far, 250 of 350 concrete panels have been installed. 

The Georgia DOT will close the westbound lane of Broad Street between Midland Avenue and Stephens Street each night through Friday, Sept. 27. Friday morning, the intersection of Stephens Street and Broad Street will be closed to through traffic on the courthouse side for slab installation. The intersection will reopen Saturday morning, Sept. 28.

During the day, sidewalk, curbing and gutter construction will continue between Candler and Stephens Street.


Get more local news delivered straight to your inbox. Sign up for free Patch newsletters and alerts.

We’ve removed the ability to reply as we work to make improvements. Learn more here